Asphalt laying explained

The process of combined road base and asphalt is recommended to hold approx an 8 ton vehicle. 

Step 1: Excavation process

Start of excavation process to form a hard stand for commercial rubbish bins.

Start of excavation

Step 2:  Compaction

Area excavated out and compacted.

070

Step 3: Road base layer

Road base going in at a depth of 100mm.

072

Step 4: Forming a level and hard base

Road base levelled out and getting compacted to form a hard base.

074

Step 5: Baking out

Road base compacted and left to bake out.

076

Step 6: Binding

Anionic emulsion sprayed down to bind new asphalt to road base.

077

Step 7: Asphalt layer

30mm of DG14 hot asphalt layed and compacted to seal area.

078

Completed Asphalt surface

Emulsion sprayed on the join and sand levelled over to stop water penetration between the 2 surfaces.

080

Step 8: Water penetration protection

Emulsion sprayed on the join and sand levelled over to stop water penetration between the 2 surfaces.